Subpart CC — the loads on a data center site are enormous and the lines are close.

Generators, chillers, cooling towers, transformers and switchgear lineups. Heavy, expensive, frequently picked over occupied areas, and often near energized overhead distribution — because the substation is being built at the same time.

The combination that kills

Crane contact with an energized overhead power line. Subpart CC devotes five sections to it (1926.1407 through 1926.1411) for exactly that reason, and on a data center campus the utility tie work and the equipment setting frequently overlap in time and space.

§ The picks

01

Standby generators. Heavy, tall, and usually set in a yard adjacent to the utility service.

02

Chillers and cooling towers. Roof or yard, large wind area, frequently over occupied space.

03

Transformers. Dense loads, tight tolerances, often placed inside a partially complete structure.

04

Switchgear lineups. Long sections, awkward rigging points, set inside the building envelope.

05

Air handlers and fan walls. Large, light, and unforgiving in wind.

§ Power line safety — the three zones

SectionSituationRequirement
1926.1407Assembly / disassembly within the prohibited zoneDe-energize and visibly ground, or maintain the minimum clearance distance
1926.1408Equipment operation up to 350 kVDetermine the line voltage. Default clearance 20 feet, or use Table A distances if the voltage is known. If neither, de-energize and ground
1926.1409Equipment operation over 350 kVGreater clearances
1926.1410Operation closer than the Table A distanceA specific, documented set of encroachment-prevention measures including a dedicated spotter, insulating link, proximity alarm and planning meeting
1926.1411Power line safety while travelling with no loadReduced but still specified clearances
The 20-foot default exists for a reason

If the line voltage has not been determined, the clearance is 20 feet — not "looks far enough." Determining the voltage requires contacting the utility, which takes time nobody has budgeted, which is why this gets skipped.

§ Ground conditions

What this means in a data center

Coordinate crane setup against the underground utility drawings, not just the surface grade. On a campus where the electrical infrastructure is being installed in parallel with the structure, the as-builts change weekly and the marked locations may be days out of date.

§ Operator certification and qualification

Common finding

A certified operator assigned to a machine configuration they have not been evaluated on. The evaluation requirement is separate from the certification and is frequently treated as satisfied by the card.