■ OSHA 1926 Construction

Subpart K — temporary power is where the citations are.

On a data center construction site the permanent electrical system is engineered, inspected and largely fine. The temporary system is assembled by whoever needed a receptacle, and it is where people get hurt.

1926.404(b)(1) — the choice

For all 125 V, single-phase, 15, 20 and 30 amp receptacle outlets on a construction site that are not part of the permanent wiring, the employer must use either ground-fault circuit interrupters or an assured equipment grounding conductor program. Not neither, and the AEGCP has specific documented requirements most sites do not meet.

§ The assured equipment grounding conductor program

If you choose AEGCP over GFCI, the standard requires all of the following — and this is why most sites simply use GFCI:

Common finding

An AEGCP declared in the site safety plan with no written description, no designated competent person, and no test records — while GFCI protection is also absent. That is two findings, not one.

§ Sections

SectionTopic
1926.402Applicability — installation safety requirements
1926.403General requirements — approval, examination, guarding of live parts, working space
1926.404Wiring design and protection — GFCI/AEGCP, grounding, overcurrent
1926.405Wiring methods, components and equipment for general use — including temporary wiring at 1926.405(a)(2)
1926.406Specific purpose equipment and installations
1926.407Hazardous (classified) locations
1926.408Special systems — over 600 V
1926.416General requirements — work practices, protection of employees, passageways and open spaces
1926.417Lockout and tagging of circuits
1926.431Maintenance of equipment
1926.432Environmental deterioration of equipment
1926.441Batteries and battery charging

§ 1926.417 — lockout and tagging of circuits

1926.417 is thinner than 1910.147 and much thinner than 70E Article 120

It requires tagging and rendering inoperative. It does not spell out verification, stored energy release, or a documented procedure. On a data center project — where the gear being worked on may be fed from a temporary source, a permanent source, or both — Article 120 is the standard that actually describes what to do.

§ Working next to live gear

What this means in a data center

The defining feature of data center construction is that it very often happens adjacent to, or inside, an operating facility. A fit-out crew installing a new data hall is working thirty feet from energized 480 V distribution serving a customer.

Two consequences. First, both 1926 and 1910 apply on the same property, and the crews need to know which side of the line they are on. Second, once any part of the new installation is energized for testing or commissioning, NFPA 70E applies to it — the equipment does not care that the project is not finished.

Physical separation, signage under 1926.200, and a clear, communicated energization status for every piece of gear is the control. More on the energization boundary →

Construction crews need 70E too

The moment it is energized, 70E applies

Qualified person training for electrical subs, commissioning agents and anyone who will work energized gear on a live project.

Onsite training Bring it onsite