■ Start here Regulatory map

Not everything on your wall is law.

Three tiers, and confusing them causes real problems — people either dismiss consensus standards because "they're not OSHA," or treat a client spec as a legal requirement. Both errors cost money.

§ Three tiers

TierExamplesEnforceable byWhat happens if you do not follow it
LawOSHA 29 CFR 1910, 1926, 1904Federal or state OSHACitation and penalty
Adopted lawNFPA 70 (NEC), building and fire codesThe AHJ, via state or local adoptionFailed inspection; no occupancy
ConsensusNFPA 70E, 70B, 110, 111, 855; IEEE 1584, 450, 3007; NETA ATS/MTS; ASTM; ANSINot directlyEstablishes recognition and feasible abatement under the General Duty Clause
ContractUptime Institute Tier, TIA-942, ASHRAE TC9.9, client and tenant specificationsThe counterpartyBreach of contract; failed audit; lost customer

§ Law

§ Consensus

The key relationship

NFPA 70E is not law. It is the industry consensus standard describing how to comply with OSHA's electrical requirements — and OSHA cites it as evidence of hazard recognition and feasible abatement. Dismissing it because "it isn't OSHA" is a misunderstanding of how enforcement actually works. How that works →

StandardCovers
NFPA 70EElectrical safety in the workplace — work practices, maintenance, special equipment. 2027 edition current.
NFPA 70 (NEC)Electrical installation. Adopted into law by jurisdiction
NFPA 70BElectrical equipment maintenance — now a standard rather than a recommended practice
NFPA 110 / 111Emergency and standby power systems / stored electrical energy systems
NFPA 855Energy storage systems — lithium-ion, thermal runaway, spacing, venting
NFPA 75 / 76Fire protection of IT equipment / telecommunications facilities
IEEE 1584Arc flash hazard calculation — the method behind your study
IEEE 450 / 1188 / 1106Battery maintenance and testing by chemistry
IEEE 3007 seriesRecommended practice for electrical safety in industrial and commercial power systems
NETA ATS / MTSAcceptance and maintenance testing specifications
ASTM F18 seriesRubber insulating equipment
ANSI Z87.1 / Z89.1 / Z358.1Eye and face / head protection / emergency eyewash

§ Contract

What this means in a data center

Contract requirements often bite harder than regulation, because the audit is annual and the consequence is losing the customer. A hyperscale tenant's EHS audit will ask for your qualification matrix, your permit history and your training records — and will not care that OSHA has not been on site in six years.

§ How they interact

01

OSHA sets the requirement. De-energize unless infeasible; protect employees from recognized hazards.

02

NFPA 70E supplies the method. Boundaries, risk assessment, permits, PPE selection, program structure.

03

The NEC determines the hazard level at design time — coordination, arc energy reduction, working space, isolation points.

04

IEEE and NETA supply the engineering — the calculation method and the test regime.

05

Contract requirements add a layer and are audited more often than any of the above.