Atlanta.
Atlanta is now the second-largest US market by inventory and arguably the fastest-moving: 918 MW absorbed in the first half of 2026, over 2 GW under construction, vacancy near 2%. Gigawatt-scale AI campuses in Fayette County are being commissioned by crews that, in many cases, have never set foot in a data center before.
The market right now
The growth is barbell-shaped: dense interconnection downtown around the 56 Marietta carrier hotel, and enormous grid-fed AI campuses to the south and west — Fayetteville, Palmetto, Douglas and Butts counties. Local politics are reshaping the map in real time; Fayetteville banned new data centers in March 2026 even as the buildings already permitted there keep rising.
- Second-largest US market by inventory behind Northern Virginia: 1,459 MW at end-2025, up 459 MW YoY (CBRE H2 2025)
- 2,076 MW under construction with vacancy near 2% (CBRE H2 2025)
- Record 918 MW absorbed in just the first six months of 2026 (JLL H1 2026)
- More than 3 GW of long-term utility power commitments support the pipeline (CBRE H2 2025)
- Named one of North America's fastest-growing data center hubs (CBRE 2025)
Every campus on the map
Solid copper markers are operating campuses; white markers are under construction; dashed outlines are announced or planned. Locations are approximate campus-level centroids compiled from public sources — county records, operator announcements, and market reports — as of August 2026. Dense clusters are grouped. Corrections are welcome through the contact page.
Operating campuses mapped
- QTS Atlanta Metro campus — QTS (Blackstone) · Downtown Atlanta. One of the world's largest single data center campuses
- QTS Fayetteville campus — QTS · Fayetteville (Fayette Co.). 13-building, ~6.2M sq ft build-out underway (Atlanta Tech News 2026)
- Google Douglas County — Google · Lithia Springs / Douglas Co.. Google's first Georgia site (2007), recycled-water cooling
- Microsoft Fairwater Atlanta — Microsoft · Fayetteville (Fayette Co.). 'AI superfactory' opened Nov 2025; 250+ MW, gigawatt-scale build-out (AJC 2025)
- Microsoft East Point — Microsoft · East Point. Azure facility in south metro cluster
- Switch 'The Keep' campus — Switch · Douglas County. 1M+ sq ft campus west of Atlanta
- T5 Lithia Springs campus — T5 Data Centers · Lithia Springs. ~1M sq ft, 300 MW campus (Atlanta Tech News)
- Digital Realty 56 Marietta / Atlanta cluster — Digital Realty · Downtown Atlanta. Region's main carrier hotel and interconnection point
- Equinix Atlanta (AT metros) — Equinix · Downtown Atlanta. Core interconnection colocation cluster
- Meta Stanton Springs campus — Meta · Social Circle (Newton Co., east metro). Multi-million sq ft owned campus operating since 2018
- DC Blox Atlanta — DC Blox · Atlanta. Regional colocation and connectivity provider
Under construction & planned
- Microsoft Fairwater expansion (Buildings 2-4) — Microsoft · Fayetteville (Fayette Co.) · under construction. Additional AI 'superfactory' buildings underway (Cleanview 2026)
- QTS Fayetteville build-out — QTS · Fayetteville · under construction. Remaining buildings of 13-building, 6.2M sq ft plan (Atlanta Tech News)
- AWS Butts County campus — Amazon Web Services · Butts County (south metro) · planned. Part of AWS's $11B Georgia infrastructure investment (AWS 2025)
- AWS Douglas County expansion — Amazon Web Services · Douglas County · planned. Second site in AWS's $11B Georgia program (AWS 2025)
- T5 South Fulton / Palmetto campus — T5 Data Centers · Palmetto / South Fulton · planned. 91-acre campus scalable to 300 MW, announced 2024 (Atlanta Tech News)
- Microsoft Palmetto campus — Microsoft · Palmetto · planned. South-metro campus; Microsoft moved in 2026 to void tax breaks, timing uncertain (AJC 2026)
- DC Blox ATL West — DC Blox · Douglas County · planned. New west-metro campus in Georgia Power queue (Interconnection.fyi)
Power
Service territory: Georgia Power · GreyStone Power EMC (Douglas County) · Cobb EMC / other EMCs.
- Georgia PSC approved special large-load tariff rules (2025) requiring 100 MW+ customers like data centers to cover their own grid costs
- Georgia Power's load forecast growth is driven overwhelmingly by data centers, spurring new generation and transmission in its IRP
- Microsoft's Fairwater Atlanta runs grid-only at gigawatt scale, leaning on Georgia Power reliability (Measured AI 2026)
The regulatory picture
Enforcement. Federal OSHA jurisdiction (no private-sector state plan); Atlanta-area offices; national emphasis programs incl. heat illness apply to construction
Licensing. Statewide electrical contractor licensing (Class I/II) via Georgia's State Construction Industry Licensing Board; no state journeyman card — worker qualification set by employers/localities
Also in play. Fayetteville banned new data centers citywide March 2026; Atlanta prohibits them near BeltLine and MARTA stations since Sept 2024 (Atlanta Tech News)
What it means for the work
The safety exposure in this market concentrates at the energization boundary: thousands of construction electricians transitioning from OSHA 1926 rules into an operating facility's NFPA 70E program, building by building, for the next several years.
Fastest-scaling US market — 2 GW under construction means huge commissioning and energization workloads with contractor crews new to data centers
Gigawatt-scale grid-only AI campuses (Fairwater) concentrate medium-voltage switching and load-bank testing at record density
Federal OSHA jurisdiction with heat-illness emphasis for Georgia summer construction
Local moratoria (Fayetteville ban, Atlanta BeltLine/MARTA limits) push new builds to exurban counties with less inspection infrastructure
Market context is half the picture. The other half is the decision walk — the nine questions the 2027 edition asks before anyone opens a door on energized gear. Run it against the task, then check the room pages in the Data Center Application Series.
NFPA 70E classes taught on the 2027 edition, against data center topology, about 55 times a year — live virtual weekly, and private onsite days in Atlanta run against your one-lines for crews of 15 or more.